Buying off-plan in Saudi Arabia: Wafi licences, escrow and your rights

The rules that protect off-plan buyers, what to check before you pay a riyal, and what happens if the developer is late or the project stalls.

By the Darna team6 min read
In this guide

In Saudi Arabia, a developer may sell homes off-plan only with a licence from the Real Estate General Authority (REGA, الهيئة العامة للعقار), under the Off-Plan Sale and Lease Law of 2023, a system REGA runs as Wafi. Buyers' payments go into the project's own escrow account at a bank, and money leaves it only against orders signed by the developer, the project's engineering consultant and its accountant. Before the sales licence, a developer may take reservations of no more than 5% of a unit's price. If delivery is late, the buyer is owed at least the rent of a similar home.

In short

  • No licence, no sale. Selling off-plan or taking buyers' money without a REGA licence can bring up to five years in prison or a SAR 10 million fine.
  • During the marketing licence (up to 180 days), a reservation can't exceed 5% of the unit's value, and it goes into escrow.
  • If the project licence never follows, REGA returns the reservations from the escrow account.
  • Late delivery earns at least a similar home's rent for a flat or villa, and at least 2% of the price a year for a plot.
  • REGA can give a late developer one extra year at most. After that, the project counts as stalled and REGA can replace the developer.

How does the off-plan licence work?

The Off-Plan Sale and Lease Law (Royal Decree M/44, 25 September 2023) and its implementing regulations of April 2024 set the rules. A developer must first be listed in REGA's Registry of Developers. It can then get a marketing licence, valid for up to 180 days, to test demand and take reservations. Selling needs the project licence.

For the project licence, the developer files the land's deed, a valid building permit, approved plans, a feasibility study, contracts with an engineering consultant and an accountant, and an agreement with a bank to open the escrow account. It also commits to start building within six months. REGA then marks the land's deed so the land can't be sold until the project is finished.

REGA publishes every licensed project in a public database: the project's name, deed and plan, location, number and type of units, the developer and its classification, the consultant, the accountant, the bank, the start and delivery dates, and progress reports. By the end of September 2025, REGA had licensed 238 off-plan projects worth more than SAR 100 billion, most of them in Riyadh, Makkah Region and the Eastern Province.

What to check before you pay

  1. The licence. Look the project up on REGA's free inquiry for licensed off-plan projects (استعلام عن المشاريع المرخصة في البيع والتأجير على الخارطة). Since May 2026, an ad for an off-plan project must also carry its licence.
  2. The escrow account. Pay only into the project's escrow account (حساب الضمان), never to the developer, a broker or a sales office. Each deposit carries a reference with your unit number.
  3. The contract. REGA publishes a model sale contract. It must set out the payment schedule, what happens if you pay late, the compensation and rent owed if the developer delivers late (including when you can cancel), and the project's duration with any extensions.
  4. The reservation. During the marketing licence, the developer can't take more than 5% of the unit's value.

Tip: Ask for the escrow account number in writing before the first transfer, and check that the bank named in REGA's database is the one holding it.

How is your money protected in escrow?

Each project has its own escrow account in riyals at a bank licensed in the Kingdom. The developer's creditors can't seize the money in it, and it can only be spent on that project. Every payment out needs an order signed by the developer, the consultant and the accountant.

Spending that isn't construction, such as marketing, administration, paying the landowner or repaying finance, is capped at 20% of the value of each unit sold. When the works are done, the accountant keeps 5% of the construction cost in the account for a year, to cover hidden defects, unless the developer provides a bank guarantee or defects insurance instead.

You can ask the developer for the accounting record of your unit, and it must give you a copy within 10 working days. The developer can't change the approved plans without the approval of REGA and the buyers.

What if the developer is late or the project stalls?

SituationWhat the rules provide
The project isn't finished by its completion date, for no reason beyond the developer's controlThe developer is late and owes compensation: for a flat or villa, at least the rent of a similar unit as set by an accredited valuer. For a developed plot, at least 2% of the sale price a year
The developer asks for more timeREGA may grant an extension of one year at most
Still not finished after the extension, or works stopped for more than 180 daysThe project is stalled. A REGA committee can appoint a manager, force the developer to replace those at fault, pay from the escrow account or bring in a replacement developer
The project can't be completedREGA can liquidate it and return the amounts paid. If an agreed liquidation fails, it goes to court
The marketing licence expires without a project licenceREGA returns the reservations held in escrow

A developer that hasn't started building six months after its licence, without an accepted excuse, can be struck off the Registry of Developers. REGA enforces the rules: in December 2025 it said it had caught 25 developers in Riyadh, Jeddah and Makkah selling off-plan and collecting money without licences, and was applying penalties that include referral to the Public Prosecution.

Tax, finance and housing support on off-plan homes

The 5% real estate transaction tax applies to off-plan purchases too, and a Saudi citizen's first-home relief covers off-plan units: see the real estate transaction tax guide. Citizens can buy an off-plan unit through Sakani with support from the Real Estate Development Fund, such as the down payment support of up to SAR 150,000 depending on salary that partner banks describe, as set out in Sakani housing support. Banks finance off-plan units too: see home loans in Saudi Arabia.

For non-Saudis, whether a resident's one home outside the designated zones can be an off-plan unit hasn't been spelled out. The rules for foreign buyers are in can foreigners buy property in Saudi Arabia. For buying a finished home, see how to buy a home in Saudi Arabia.

Frequently asked questions

Is buying off-plan safe in Saudi Arabia?

A licensed project gives you three protections in law: your money sits in the project's escrow account, it is released only against signed payment orders, and late delivery earns compensation. Buying from an unlicensed project gives you none of them, so check the licence first.

How do I check if an off-plan project is licensed in Saudi Arabia?

Use REGA's free inquiry for licensed off-plan projects on its website. A licensed project shows its developer, bank, consultant, accountant and delivery date.

What happens if the developer delays delivery?

For a flat or villa, the developer owes at least the rent of a similar home for the delay, as set by an accredited valuer. REGA can grant at most one extra year, after which the project counts as stalled.

Can I get my money back from an off-plan project?

Yes, in set cases: REGA returns reservations if the project never gets its licence, and it can liquidate a stalled project and return what buyers paid. Your contract also sets when you can cancel for late delivery.

How much can a developer take to reserve an off-plan unit?

No more than 5% of the unit's value during the marketing licence, paid into the escrow account.

Sources

This guide is general information, not legal or tax advice. Fees and procedures change, so check with a lawyer before you sign or pay.